Contract Manager of the task called “Construction of an athletic stadium with a recreational and sport area within the framework of the ”Odra-Velo”-System in Siechnice.
In the period from February to November 2014 Prime Project will carry out a function of Contract Manager with Investor’s Supervision in the construction, sanitary, road and electrical discipline over the construction of an athletic stadium with a recreational and sport area in Siechnice, an investment financed from the Regional Operational Programme for Dolnośląskie Voivodeship 2007-2013.
Size of the objects total – 42 412 m²,
cubic capacity of the objects total – 1 105,65 m³,